Minuano

Minuano Project

Minuano

Minuano Project


Timeline

  • December 2019
    Award of the lot in the ANEEL transmission auction (02/2019)
  • July 2023
    Obtaining the Installation Environmental License issued by the State Foundation for Environmental Protection (Fepam) of Rio Grande do Sul
  • March 2024
    Obtaining the Operation License for the Caxias Norte Substation
  • December 2024
    Energization (ANEEL deadline)